Activity packages

In March 2022, an extension of the project implementation period by 11 months took place, by signing an additional act
In July 2023, an extension of the project implementation period by 5 months took place, by signing an additional act.
In December 2023, an extension of the implementation period of the project until 31.12.2024 was approved, based on the Managing Authority for the Competitiveness Operational Programme instruction no. 72/2023
The List of work packages:

WP1, Expansion of experimental air testing facilities, deals with the design, procurement, manufacturing, installation, and commissioning activities related to expanding the air experimental test rig. WP1 will receive control input from WP5 and interface information from WP2 and WP3. WP1 will provide interface information to WP2, as well as dissemination materials for WP4 and feedback to WP5.

WP2, Development of air supply station, includes the manufacturing, procurement, installation, commissioning and testing activities related to the new air supply station through the project. WP2 will receive control input from WP5. WP2 will provide interface information to WP1 and WP3, and dissemination materials for WP4 and feedback to WP5.

WP3, Diversification of instrumentation, gathers activities related to purchasing, installing, commissioning and testing additional sensors, command and control equipments, for the existing air infrastructure, as well as with using the new infrastructure to provide validation data for assessing the accuracy of the measurement equipment installed in WP 2. WP3 will receive control input from WP5 and interface information from WP2. WP3 will provide dissemination materials for WP4 and feedback to WP5.

WP4, Dissemination and exploitation, deals with disseminating the project results and planning for the exploitation of its achievements. WP5 receives input from WP1, WP2 and WP3, and receives control input from WP 4.

WP5, Management, includes project management activities. WP4 provides control input to all the other WPs, and receives feedback from the same.